Option A - Shield Method–
• It is used in soft soil for driving a tunnel through water bearing strata.
• It is an equipment which acts as a bridge with roof for workers. It consist of a circular steel ring with a transverse diaphragm. The essential part of shield are hood, tail, cutting edges and propelling jacks.
• The excavation and lining of tunnel can be carried out under protection of shield.
Different methods of tunnel construction suitable for rocks–
• Drift method–In this method, a drift is first driven of appropriate size, usually of 3000 mm. The drill holes are provided all round the drift in entire cross section of tunnel.
• Full face method–The full face method is adopted only for small tunnels whose dimensions do not exceed about 3 m.
• Heading and Bench method–This is the method usually adopted for all railway tunnels.
A. Shield Method–
• It is used in soft soil for driving a tunnel through water bearing strata.
• It is an equipment which acts as a bridge with roof for workers. It consist of a circular steel ring with a transverse diaphragm. The essential part of shield are hood, tail, cutting edges and propelling jacks.
• The excavation and lining of tunnel can be carried out under protection of shield.
Different methods of tunnel construction suitable for rocks–
• Drift method–In this method, a drift is first driven of appropriate size, usually of 3000 mm. The drill holes are provided all round the drift in entire cross section of tunnel.
• Full face method–The full face method is adopted only for small tunnels whose dimensions do not exceed about 3 m.
• Heading and Bench method–This is the method usually adopted for all railway tunnels.