Q: A contractor takes on the task of building a wall in 50 days. He hires 50 men but after 25 days he find that only 40% of the work is complete. How many more men must he hire to finish the work 10 days ahead of schedule?
  • A. 75
  • B. 95
  • C. 115
  • D. 125
Correct Answer: Option A -