Q: A contractor takes on the task of building a wall in 50 days. He hires 50 men but after 25 days he find that only 40% of the work is complete. How many more men must he hire to finish the work 10 days ahead of schedule?
A.
75
B.
95
C.
115
D.
125
Correct Answer:
Option A -