Q: 100 worker can dig a 2000m long canal in 25 days by working 8 hour daily. Find the number of worker required to dig a similar canal of 2800 m long in 32 days working 5 hours daily?
  • A. 175
  • B. 170
  • C. 165
  • D. 180
Correct Answer: Option A -
answer image

Explanations:

explanation image