Q: Which of the following is a type of detailed estimate?
  • A. Service unit method
  • B. Revised estimate
  • C. Plinth area rate method
  • D. Cubical content method
Correct Answer: Option B - Types of estimate– 1.Preliminary/approximate/abstract/rough cost estimate • Plinth are estimate • Cubical rate estimate • Unit rate method/serve unit method • Typical bay method 2. Detailed or Item rate estimate– • Unit quantity method • Total quantity method • Supplementary estimate • Revised estimate • Annual repair estimate • Supplementary and revised estimate • Complete estimate
B. Types of estimate– 1.Preliminary/approximate/abstract/rough cost estimate • Plinth are estimate • Cubical rate estimate • Unit rate method/serve unit method • Typical bay method 2. Detailed or Item rate estimate– • Unit quantity method • Total quantity method • Supplementary estimate • Revised estimate • Annual repair estimate • Supplementary and revised estimate • Complete estimate

Explanations:

Types of estimate– 1.Preliminary/approximate/abstract/rough cost estimate • Plinth are estimate • Cubical rate estimate • Unit rate method/serve unit method • Typical bay method 2. Detailed or Item rate estimate– • Unit quantity method • Total quantity method • Supplementary estimate • Revised estimate • Annual repair estimate • Supplementary and revised estimate • Complete estimate