Q: Which estimate is prepared for administrative approval and technical sanction?
  • A. Detailed estimate
  • B. Supplementary estimate
  • C. Complete estimate
  • D. Revised estimate
Correct Answer: Option A - After getting administrative approval and technical sanction on rough cost estimate, detailed estimates are prepared. • The detailed estimate shall also provide for the cost of approach road, water supply, electric installations and acquisition of land etc. so as to call it a comprehensive estimate.
A. After getting administrative approval and technical sanction on rough cost estimate, detailed estimates are prepared. • The detailed estimate shall also provide for the cost of approach road, water supply, electric installations and acquisition of land etc. so as to call it a comprehensive estimate.

Explanations:

After getting administrative approval and technical sanction on rough cost estimate, detailed estimates are prepared. • The detailed estimate shall also provide for the cost of approach road, water supply, electric installations and acquisition of land etc. so as to call it a comprehensive estimate.