Correct Answer:
Option B - Water/cement ratio per complete hydration of cement is 0.35-0.45.
• Approximately 23% water by weight is required for hydration.
• To complete all chemical reaction and 15% water is entrapped in between the voids of cement.
• The total water required for complete hydration and workability is 38% by weight.
B. Water/cement ratio per complete hydration of cement is 0.35-0.45.
• Approximately 23% water by weight is required for hydration.
• To complete all chemical reaction and 15% water is entrapped in between the voids of cement.
• The total water required for complete hydration and workability is 38% by weight.