Q: The formal acceptance of the proposal of a work by the concerned department is known as ___________.
  • A. proposal approval
  • B. administrative approval
  • C. technical approval
  • D. preliminary approval
Correct Answer: Option B - Administrative approval–Formal acceptance of the proposed work or project by the competent authority is called the administrative approval of work and it is the duty of the concerned officers to obtain it. Technical approval–For every work proposed to be carried out except petty works and petty repairs and repair for which a lump sum provision has been sanctioned by the super intending engineer, a properly detailed estimate must be prepared for sanction by the competent authority.
B. Administrative approval–Formal acceptance of the proposed work or project by the competent authority is called the administrative approval of work and it is the duty of the concerned officers to obtain it. Technical approval–For every work proposed to be carried out except petty works and petty repairs and repair for which a lump sum provision has been sanctioned by the super intending engineer, a properly detailed estimate must be prepared for sanction by the competent authority.

Explanations:

Administrative approval–Formal acceptance of the proposed work or project by the competent authority is called the administrative approval of work and it is the duty of the concerned officers to obtain it. Technical approval–For every work proposed to be carried out except petty works and petty repairs and repair for which a lump sum provision has been sanctioned by the super intending engineer, a properly detailed estimate must be prepared for sanction by the competent authority.