Correct Answer:
Option C - Pre-tender stage–
• Initiation of proposal and preparation of schemes..
• Technical sanction
• Acceptance of proposal in accordance to its feasibility and acquisition of land.
• Survey of site
• Preparation of drawing, design estimate
• Accord of administrative approval and allotments of funds.