Correct Answer:
Option A - Cubical contents method–This method is generally used for multi-storeyed buildings.
• It is more accurate than the plinth area method and unit base method.
• The cost of a structure is calculated approximately as the total cubical contents multiplied by local cubic rate.
A. Cubical contents method–This method is generally used for multi-storeyed buildings.
• It is more accurate than the plinth area method and unit base method.
• The cost of a structure is calculated approximately as the total cubical contents multiplied by local cubic rate.