Correct Answer:
Option D - The concrete members are heated by steam at 93°C either at low pressure or high pressure. In low pressure steam curing about 70% of the 28 day compressive strength of concrete can be obtained in about 16-24 hours. High pressure steam curing is usually applied to precast.
Concrete members and gives 28 day compressive strength at 24 hours.
D. The concrete members are heated by steam at 93°C either at low pressure or high pressure. In low pressure steam curing about 70% of the 28 day compressive strength of concrete can be obtained in about 16-24 hours. High pressure steam curing is usually applied to precast.
Concrete members and gives 28 day compressive strength at 24 hours.