Q: As per IS 456 : 2000, what is the minimum period before striking formwork for vertical formworks to columns, walls and beams?
  • A. 7 days
  • B. 7 hours
  • C. 16 – 24 days
  • D. 16 – 24 hours
Correct Answer: Option D -