Correct Answer:
Option A - Estimation of air content–Approximate amount of entrapped air to be expected in normal (non air-entrained) concrete is given as per IS 10262-2019.
Table 3–
Nominal maximum size Entrapped air, as % of
of aggregate (mm) volume of concrete
10 1.5
20 1.0
40 0.8
A. Estimation of air content–Approximate amount of entrapped air to be expected in normal (non air-entrained) concrete is given as per IS 10262-2019.
Table 3–
Nominal maximum size Entrapped air, as % of
of aggregate (mm) volume of concrete
10 1.5
20 1.0
40 0.8