search
Q: According to IS : 456 : 2000, if 46 cubic metres quantity of M25 grade of concrete is required at a site, the minimum number of cube samples that should be taken from the site are____.
  • A. 9
  • B. 8
  • C. 4
  • D. 7
Correct Answer: Option C -
answer image

Explanations:

explanation image