Correct Answer:
Option A - A revised estimate is prepared when the sanctioned estimate is likely to exceed more than 5% without structural alternation or when the expenditure of works exceeds than 10% of the administrative approval.
A. A revised estimate is prepared when the sanctioned estimate is likely to exceed more than 5% without structural alternation or when the expenditure of works exceeds than 10% of the administrative approval.