Correct Answer:
Option D - The construction joints are provided at locations where the construction is stopped either at the end of the day or for any other reason.
The provision of a construction joint becomes necessary to ensure proper bond between the old work and the new one.
The construction joint should be located along or near the planes of the least bending moment and shear force.
D. The construction joints are provided at locations where the construction is stopped either at the end of the day or for any other reason.
The provision of a construction joint becomes necessary to ensure proper bond between the old work and the new one.
The construction joint should be located along or near the planes of the least bending moment and shear force.