Q: A and B together can complete a work in 24 days. A alone can complete the same work in 40 days. In how many days can B alone complete the same work?
  • A. 40 Days
  • B. 60 Days
  • C. 56 Days
  • D. 16 Days
Correct Answer: Option B -
answer image

Explanations:

explanation image