Q: A and B do a piece of work in 12 days and 18 days respectively. They worked together for 4 days after which B was replaced by C and remaining work was completed by A and C in next 4 days. In how many days will C alone complete 50% of the same work?
A.
21
B.
18
C.
24
D.
36
Correct Answer:
Option B -
Explanations: