Q: A and B can finish a project in 10 days, B and C can finish it in 20 days, and C and A can finish it in 30 days. If A, B and C work together, then they will finish the project in:
  • A.
    option image
  • B.
    option image
  • C.
    option image
  • D.
    option image
Correct Answer: Option A -
answer image

Explanations:

explanation image