Correct Answer:
Option D - Workability test is done by-
(i) Slump test
(ii) Compaction test
(iii) Vee-bee consistometer test
(iv) Flow test
(v) Kelly ball test
Non- destructive testing machine method for concrete-
(i) Rebounded method
(ii) Pull- out testing
(iii) Ultra- sonic pulse velocity etc.
D. Workability test is done by-
(i) Slump test
(ii) Compaction test
(iii) Vee-bee consistometer test
(iv) Flow test
(v) Kelly ball test
Non- destructive testing machine method for concrete-
(i) Rebounded method
(ii) Pull- out testing
(iii) Ultra- sonic pulse velocity etc.