Q: When not specified, the volume of steel in R.C.C. work is taken as:
  • A. 1% to 1.6% of R.C.C. volume
  • B. 2% to 4% of R.C.C. volume
  • C. 4% to 6% of R.C.C. volume
  • D. 0.6% to 1% of R.C.C. volume
Correct Answer: Option D - When not specified the volume of steel in R.C.C. work taken as 0.6 to 1% of R.C.C. Volume. Quantity of steel– Slabs – 0.7 to 1% Beam – 1% to 2% Columns – 1% to 5%
D. When not specified the volume of steel in R.C.C. work taken as 0.6 to 1% of R.C.C. Volume. Quantity of steel– Slabs – 0.7 to 1% Beam – 1% to 2% Columns – 1% to 5%

Explanations:

When not specified the volume of steel in R.C.C. work taken as 0.6 to 1% of R.C.C. Volume. Quantity of steel– Slabs – 0.7 to 1% Beam – 1% to 2% Columns – 1% to 5%