Correct Answer:
Option D - The standard consistency of cement test should be performed as per IS code 4031 Part 4 specifications by the Vicat apparatus mentioned in IS code 5513. • The required water for making cement paste can be found by the plunger of the vicat apparatus penetrating the cement past about 5 mm to 7 mm bottom from the Vicat mould.
D. The standard consistency of cement test should be performed as per IS code 4031 Part 4 specifications by the Vicat apparatus mentioned in IS code 5513. • The required water for making cement paste can be found by the plunger of the vicat apparatus penetrating the cement past about 5 mm to 7 mm bottom from the Vicat mould.