Correct Answer:
Option A - Pointing work is measured in square metres (m²) pointing is the finishing of mortar joints in brick or stone masonry construction. It is done for cement mortar and lime mortar joints.
• Reinforcement in cement concrete in beams, slabs and lintels are measured in cubic metres (cub.m).
• DPC. (Damp Proof Course); plastering, white washing are measured in square metres (m²).
A. Pointing work is measured in square metres (m²) pointing is the finishing of mortar joints in brick or stone masonry construction. It is done for cement mortar and lime mortar joints.
• Reinforcement in cement concrete in beams, slabs and lintels are measured in cubic metres (cub.m).
• DPC. (Damp Proof Course); plastering, white washing are measured in square metres (m²).