Correct Answer:
Option C - Toothing– It is the termination of the wall in such a fashion that each alternate course at the end projects, in order to provide adequate bond if the wall is continued horizontal at a later stage.
• Shear cracks between the main wall and cross-wall can be corrected using toothing.
C. Toothing– It is the termination of the wall in such a fashion that each alternate course at the end projects, in order to provide adequate bond if the wall is continued horizontal at a later stage.
• Shear cracks between the main wall and cross-wall can be corrected using toothing.