Correct Answer:
Option C - The approximate volume of stone required for 100 m³ of rubble stone masonry will be 125 m³.
Masonry of rubble stone (per cubic meter)
(i) Stone ballast - 1.25 cum
(ii) Cement mortar (dry) - 0.42 cum
Ashlar masonry (per cum)
(i) Stone (without dressing) – 1.33 cum
(ii) Stone (dressing) - 1.00 cum
(iii) Cement mortar (dry) - 0.20 cum
C. The approximate volume of stone required for 100 m³ of rubble stone masonry will be 125 m³.
Masonry of rubble stone (per cubic meter)
(i) Stone ballast - 1.25 cum
(ii) Cement mortar (dry) - 0.42 cum
Ashlar masonry (per cum)
(i) Stone (without dressing) – 1.33 cum
(ii) Stone (dressing) - 1.00 cum
(iii) Cement mortar (dry) - 0.20 cum