Q: In the process of hydration of OPC, to complete all chemical reaction, the water requirement (expressed as the percentage of cement) is .........
A.
5 to 8%
B.
8 to 16%
C.
20 to 25%
D.
35 to 45%
Correct Answer:
Option C - About an average 23% of water by weight of cement is required for complete hydration of portland cement and 15% of water by weight of cement is required to fill the gel process.
C. About an average 23% of water by weight of cement is required for complete hydration of portland cement and 15% of water by weight of cement is required to fill the gel process.
Explanations:
About an average 23% of water by weight of cement is required for complete hydration of portland cement and 15% of water by weight of cement is required to fill the gel process.