Q: If 6 men and 8 boys can do a piece of work in 10 days, while 26 men and 48 boys can do the same work in 2 days, the time taken by 25 boys in doing the same type of work will be:
A.
6 days/6 दिन
B.
8 days/8 दिन
C.
5 days/5 दिन
D.
4 days/4 दिन
Correct Answer:
Option B -
Explanations: