Q: Identify the method of road construction which has the following properties: i. Has large number of transverse joints ii. During rains, the water gets collected between the finished bays iii. Needs complete diversion of traffic
A.
Continuous bay method
B.
Expansion joint method
C.
Dowel bar method
D.
Alternate bay method
Correct Answer:
Option D -
Explanations: