Correct Answer:
Option B - Tools and Plant (T & P)– For the execution of big works, provision for the purchase of machinery etc. For big projects an amount 1% to 1.5% of the estimated cost is also provided to purchase special tools and plants for specific purposes.
Contingency Fund– This estimated cost is increased by 3% to 5% for all unforeseen expenditure.
Note : The commission has rejected the question in revised answer key.
B. Tools and Plant (T & P)– For the execution of big works, provision for the purchase of machinery etc. For big projects an amount 1% to 1.5% of the estimated cost is also provided to purchase special tools and plants for specific purposes.
Contingency Fund– This estimated cost is increased by 3% to 5% for all unforeseen expenditure.
Note : The commission has rejected the question in revised answer key.