Q: Among the following, the correct sequence of WBM construction will be: i. Preparation of subgrade ii. Spreading of Coarse aggregates iii. Application of binding material iv. Application of screenings v. Provision of lateral confinement
A.
i, iv, ii, iii, v
B.
i, ii, iv, iii, v
C.
ii, i, iv, v, iii
D.
i, v, ii, iv, iii
Correct Answer:
Option D - The proper sequences of water bond macadam(WBM) road construction:
(1) Preparation of subgrade
(2) Provision of lateral confinement
(3) Spreading of coarse aggregate
(4) Application of screenings
(5) Application of binding material
D. The proper sequences of water bond macadam(WBM) road construction:
(1) Preparation of subgrade
(2) Provision of lateral confinement
(3) Spreading of coarse aggregate
(4) Application of screenings
(5) Application of binding material
Explanations:
The proper sequences of water bond macadam(WBM) road construction:
(1) Preparation of subgrade
(2) Provision of lateral confinement
(3) Spreading of coarse aggregate
(4) Application of screenings
(5) Application of binding material
Download Our App
Download our app to know more Lorem ipsum dolor sit amet consectetur adipisicing elit.
Excepturi, esse.
YOU ARE NOT LOGIN
Unlocking possibilities: Login required for a world of personalized
experiences.