Q: A and B together can complete a work in 48 days. A is four time as efficient as B. In how many days can B alone complete the work?
  • A. 240 Days
  • B. 220 Days
  • C. 120 Days
  • D. 320 Days
Correct Answer: Option A -
answer image

Explanations:

explanation image